How should a Nation take handover of new homes on reserve?

Handover is the last point where a Nation has full leverage over a builder, so treat it as a process, not a ribbon cutting. Before families move in, get the required inspections, a signed deficiency list, commissioned heating and ventilation, and the manuals and warranty papers. On reserve, the provincial new home warranty that protects buyers off reserve often does not apply, so the warranty you get is the one your contract spells out.

This article is general information for housing managers and technical staff, not legal advice. Confirm the rules for your project with ISC, CMHC, your lands office and your own lawyer.

What does handover actually involve?

Most capital projects close in two steps. Indigenous Services Canada's instructions for its Capital Projects Report describe a Provisional Certificate of Completion for a facility that has been "completed to the stage where it is safely being used for the intended purpose, but still has outstanding work." At that point a substantial completion certificate or certificate of occupancy can be attached, on the condition that the outstanding work is finished within a reasonable time, and "A portion of project funding would be held back until 100% completion."

The Final Certificate of Completion comes later. The same instructions say that for new facilities there is usually a warranty period, and "Upon the expiration of the warranty period, a final inspection is carried out and if all deficiencies have been rectified, the Final Certificate of Completion is issued." ISC uses the report to trigger warranty periods and to set up the new asset so that operations and maintenance funding can begin. The report is due within 90 days of provisional or final completion (Manitoba region has its own March 31 date). The version opened for this article is the 2020-2021 form, so check your funding agreement and ISC regional office for the current one.

So there are really three moments to plan for: move-in (substantial completion), the end of the warranty period, and the final inspection that closes the file. Each needs its own paperwork.

Which inspections and walkthroughs come before move-in?

For homes funded under CMHC's On-Reserve Non-Profit Housing Program (Section 95), CMHC's page on building code compliance for First Nation housing lists three inspection points for the Certificate of Building Code Compliance: a pre-backfill inspection (foundation stage), a pre-drywall inspection (framing, rough-in and insulation/vapour barriers stage) and a final inspection. The inspector must hold credentials from a recognized professional industry organization, and a professional engineer or architect is considered qualified. The First Nation pays for these inspections, but CMHC says the costs "are considered eligible expenses" under the program.

ISC's completion instructions add that "Prior to use, the facility must be inspected to ensure that all work meets the technical specifications." For housing, a CMHC-approved inspector must inspect the house and a Health Canada inspector must approve the septic system, and each inspector should give the First Nation a separate official report to attach to the certificate of completion. The checklist of completion documents also includes electrical inspection reports, fire commissioner reports, water and sewage testing, and a certificate of occupancy where one applies.

Alongside the formal inspections, hold your own walkthrough with the builder's site lead. A practical approach:

  1. Walk every home with the contract drawings and specifications, not from memory. Note the unit number, room and item for every deficiency.
  2. Run every fixture, appliance, door, window and switch. Check that the heating system and ventilation are running and controllable.
  3. Photograph each item and agree on a written deficiency list that both sides sign, with a date for each fix.
  4. Separate items that stop occupancy (no heat, no water, safety issues) from cosmetic items that can be fixed after move-in.
  5. Re-walk the list when the builder says items are done, and sign them off one by one.

The CMHC Section 95 operations guide includes a unit inspection form with a line for "Repairs to be completed on initial occupancy." Using a form like it at handover gives you a baseline record for each home before anyone moves in.

What should commissioning of heating and ventilation include?

Heat and fresh air are the systems most likely to fail quietly after handover, and in a northern winter a problem found in January is an emergency. CMHC's HRV and ERV guide for multi-unit buildings describes commissioning as the process through which a system "is verified and adjusted so that it performs per the original design intent." Its simplified commissioning process includes inspecting components, testing and balancing the system to the design air flow rates, functional testing in all modes of operation, and a summary report or checklist showing every component is working as designed.

The guide is written for multi-unit buildings, but its handover advice applies to any home: "At project completion, the system installer should provide the building or suite owner, property manager or service contractor with product data, warranty information and the HRV/ERV operation and maintenance (O and M) manual." Ask for the same in your contract, along with the measured air flows from balancing and the furnace or boiler start-up record.

Commissioning also means teaching people how to live with the system. CMHC's HRV and ERV guide for property managers says the unit "is intended to operate continuously, and shutting it off for a long time can lead to a buildup of pollutants and humidity." It recommends cleaning or replacing filters every 3 months and annual servicing by an HRAI- or TECA-accredited mechanical contractor. Book a short session for each household at move-in, and keep a sign-off sheet. For more on ventilation itself, see our article on HRVs and indoor air.

How do holdbacks work at substantial completion?

ISC's tendering policy for federally funded capital projects defines a holdback as "a contractually agreed-upon percentage of money that is withheld from the progress payments" and refers to "the industry standard 10% deficiency/builder's lien holdback." Bonds and security amounts are covered in our article on how First Nations tender housing and building projects; here the point is how the holdback is used at handover.

ISC's completion instructions describe a deficiency holdback "retained until any deficiencies have been rectified." Your contract should say exactly when and how much is released: for example, part at substantial completion once the occupancy-stopping items are fixed, and the rest when the deficiency list is fully signed off and the manuals, as-built drawings and warranty documents are delivered. Tie the release to documents, not to a calendar date.

Off reserve, provincial builders' lien or prompt payment laws set many holdback and substantial performance rules. On reserve, section 89(1) of the Indian Act states that the real and personal property of an Indian or a band on a reserve "is not subject to charge, pledge, mortgage, attachment, levy, seizure, distress or execution" in favour of anyone other than an Indian or a band. How that interacts with a provincial lien statute on your project is a question for your lawyer. The practical lesson is to write the holdback amount, release triggers and deficiency process into the contract itself rather than assume a provincial act fills the gaps.

Do provincial new home warranty programs cover homes on reserve?

Often they do not. Here is what the provincial sources say:

  • Alberta. The province's new home warranty page states: "The act does not apply to homes built on or relocated to federal lands such as First Nations reserves or National Parks." It adds that obtaining warranty "is considered a best practice," with coverage of key components "for up to a period of 10 years."
  • British Columbia. BC Housing says "First Nations reserve lands are under federal jurisdiction and are not subject to the Act and Regulations" on its third-party home warranty insurance page, and builders on reserve "may voluntarily become licensed or offer home warranty insurance." Homes on Treaty First Nations lands are different: they are subject to the Homeowner Protection Act once the treaty is passed into law and implemented. Off reserve, BC's home warranty insurance page describes 2-5-10 coverage: materials and labour, five years on the building envelope and ten years on structure.
  • Manitoba. The New Home Warranty Act as enacted says nothing about reserves either way; it states "This Act binds the Crown" and lets the province exempt areas by regulation. The province's 2016 announcement described minimum coverage of one year for materials, labour and design, two years for systems and the building envelope, and seven years for structure. Ask Manitoba's Consumer Protection Office and your lawyer whether it reaches homes on your reserve before you rely on it.
  • Saskatchewan. CMHC's Saskatchewan fact sheet, published in 2018, answers the question of whether condominium developers must provide a new home warranty with "No, but there are several new home warranty programs in Saskatchewan to which many developers belong." Coverage there depends on what the builder chooses to join and what your contract requires.

The common thread: on reserve, warranty is a contract term you negotiate, not a protection you can assume.

What should a Nation put in its contract instead?

Use the provincial programs as a benchmark for what reasonable coverage looks like, then write it into the contract. Points to cover, with your lawyer:

  • Coverage periods by component, for example materials and labour, mechanical, electrical and plumbing systems, the building envelope, and structure, each with a stated length. BC's 2-5-10 and Manitoba's 1-2-7 structures are useful reference points.
  • When each period starts: substantial completion, occupancy of each unit, or another defined date. ISC's instructions note that a warranty period "could commence once the substantial or construction completion certificate has been issued."
  • Third-party backing: whether the builder will enrol the homes in a warranty insurance program voluntarily (BC Housing notes builders on reserve may do so), or provide a warranty bond or extended holdback instead.
  • Response times for emergency items (no heat, no water, safety) versus routine items, and what happens if the builder does not respond, including your right to hire someone else and recover the cost.
  • Manufacturer warranties on furnaces, HRVs, water heaters and appliances, assigned to the Nation, with registration done at handover.
  • Remote-site logistics: who pays for travel, freight and seasonal access when warranty work is needed in a fly-in or winter-road community.
  • A final inspection before the warranty ends, matching the ISC step that leads to the Final Certificate of Completion.
  • Handover documents as a condition of final payment: O&M manuals, commissioning reports, as-built drawings, inspection reports, warranty certificates and a contact list for service.

How do warranty claims work, and what records should you keep?

Without a provincial program, claims run through whatever process your contract sets out, so make it simple: one named contact at the Nation, one at the builder, a written claim form, and a log of every claim with dates for report, response and repair. Report problems in writing as soon as they appear, and walk every home again a month or two before each warranty period ends so nothing is missed.

CMHC's Section 95 operations guide recommends maintenance files for each unit and notes they can hold information on major equipment, including "makes, models, serial numbers, servicing schedules, warranty requirements." It also warns that the federal subsidy will be suspended if units are not maintained or there is significant evidence of deferred maintenance. A warranty file per home, started at handover, feeds straight into that maintenance file. Our article on running a housing maintenance program on reserve covers the longer-term side.

Where does a builder fit in?

Herauf Modular, a division of Herauf Enterprises, builds homes and community buildings as finished sections indoors in its plants across Western Canada, then delivers and sets them on site. Builds are manufactured in as little as 16 weeks once the issued-for-construction (IFC) package is signed off and permit and engineering approval are in, with foundations, pads and services prepared on site at the same time, and set-up on site takes days. Every unit meets or exceeds CSA A277 and the National Building Code for climate zones 6 through 8.

Herauf has delivered youth transitional homes and a child and family services building to St. Theresa Point First Nation over the winter ice road, and homes for Buffalo Lake Métis Settlement with CMHC and government agencies. Ask any builder, Herauf included, to set out its warranty terms, commissioning steps and handover documents in writing before you sign. To talk about a project, send an enquiry; Herauf replies within one business day.

This guide is general information, not legal or financial advice. Program rules change: confirm the details with the program, your Indigenous Services Canada regional office or CMHC before relying on them. Herauf does not administer any program or apply on a community's behalf.

  • handover
  • warranty
  • deficiencies
  • commissioning
  • holdbacks

Questions, answered.

Does Alberta's new home warranty apply to homes on a First Nations reserve?

No. Alberta's new home warranty page states that the act does not apply to homes built on or relocated to federal lands such as First Nations reserves or National Parks. The province says obtaining warranty is still considered a best practice, so a Nation should set warranty terms in its construction contract.

Do homes on reserve in BC need 2-5-10 home warranty insurance?

BC Housing says First Nations reserve lands are under federal jurisdiction and are not subject to the Homeowner Protection Act and Regulations, though builders may voluntarily become licensed or offer home warranty insurance. Homes on Treaty First Nations lands are subject to the Act once the treaty is passed into law and implemented.

What inspections does CMHC require for Section 95 homes?

CMHC lists three inspection points for the Certificate of Building Code Compliance: pre-backfill (foundation), pre-drywall (framing, rough-in and insulation/vapour barriers) and a final inspection, done by a qualified inspector. The First Nation pays, but the costs are eligible expenses under the On-Reserve Non-Profit Housing Program.

When does ISC issue the Final Certificate of Completion?

ISC's Capital Projects Report instructions say that when the warranty period expires, a final inspection is carried out, and if all deficiencies have been rectified, the Final Certificate of Completion is issued. The asset then enters the full operations and maintenance phase. Check your funding agreement for current requirements.

What should the builder hand over for the HRV?

CMHC's HRV and ERV guide says that at project completion the installer should provide product data, warranty information and the operation and maintenance manual, plus any training particular to the unit. Ask for the balancing results too, and train each household at move-in.

Sources.

Every figure and program rule above comes from these pages, opened and read when the guide was written.

  1. Capital Projects Report instructions (DCI 460671, 2020-2021), Indigenous Services Canada.
  2. Building Code Compliance for First Nation Housing, CMHC (page modified 2018-03-31).
  3. On-Reserve Non Profit Housing Program (Section 95) Operations Guide, CMHC (page modified 2023-04-18).
  4. HRV and ERV Guide for Multi-Unit Residential Buildings, CMHC.
  5. Heat Recovery and Energy Recovery Ventilators: A Guide for Property Managers, CMHC.
  6. Policy on tendering for First Nations' federally funded capital projects, Indigenous Services Canada (page modified 2026-07-15).
  7. Indian Act, section 89, Justice Laws Website (page modified 2026-10-29).
  8. New home warranty, Government of Alberta.
  9. Third-party Home Warranty Insurance, BC Housing (page modified 2026-09-22).
  10. Home Warranty Insurance: What Homeowners Need to Know, BC Housing (page modified 2026-09-22).
  11. The New Home Warranty Act, S.M. 2013, c. 23, Government of Manitoba.
  12. Province advises New Home Warranty Act to come into force (news release, 2016-01-19), Government of Manitoba (page modified 2016-01-19).
  13. Saskatchewan Fact Sheet (condominium buying guide), CMHC (page modified 2018-03-31).